Value Viewer - Portfolio dashboard

IRR
14.28 Complete (success)
30% Complete (warning)
50% Complete (danger)

-50%

-25%

0%

+25%

+50%

Strategic
Operational

0%

25%

50%

75%

100%

Project financials by stage

Stage Planing Execution Complete Post
Poned
Cancelled Total
Projects 4 6 0 3 4 17
IRR >=Hurdle Rate 2 2 3 4 11
IRR < Hurdle Rate and> 0 2 1 3
IRR <=0 3 3

Performance of in-flight projects

Overall performance Red Yellow Green
Projects 1 3 2
Investment $k $1,000 $3,000 $500
NPV $k $250 $500 $52
IRR 25% 17% 10%
Time performance 2 4 0
Cost performamce 0 2 4

Delivery Risk vs Benefit Risk

Projects Low benefit Risk Med. Benefit Risk High Benefit Risk
High Delivery Risk 1 2 4
Medium Delivery Risk 1 2 1
Low Delivery Risk 2 2
Description of the risk Probab. Impact Comments
Regulatory projects in May 2018 may exceed the provision in the portfolio Med-High Would reduce value of the portfolio Provision increased in review
Portfolio resource may be redeployed to projects in other portfolios High Delayed, postpone, cancel projects Assessing impact vs benefit of change
Description of the milestone Project or program Set Date Status Comments or updates
MVP for user experience ABC Project CXY SEP-18 On track On track but at risk due to resources
Completion of all XYZ relates projects All XYZ related MAY-18 Complete
Completion of all regulatory projects All regulatory OCT-18 Delayed Current forecast is end of Nov due to changes
Month $k EOY $k EAC $k
Budget $700 $9,000 $12,000
Forecast/Actual $850 $10,500 $15,000
Variance -21% -17% -25%